INDUSTRY: Mining

PROJECT: Kennecott Copper Mine Conveyors - 2002

PROJECT SUMMARY:

Performed the structural/mechanical installations on a 10,000 TPH in-pit crusher relocation. Work activities included the assemblies of transfer stations, 72" conveyors, 120" belt feeder, chute and plate work, electrical E-House installations and start-up activities.

PROJECT HIGHLIGHTS:

  • Early Completion & Safety Bonus were realized
  • Work performed in an existing/operating mine
  • 10 day - 24 hour/day crusher shutdown
  • Utilized computer generated Critical Lift Plans

 